Details

Invoice


CreationDate
10/18/2024
Vehicle
D179 - Alexis Corona Leyva
Work
10-11-2024 to 10-17-2024
Check
Direct Pay
Bonus
Toll
Bonus + Toll
PDF (TestA TestRW) - EXCEL (TestA TestRW) -
  
Number Vehicle WorkFrom Order Product Ton Price Total
31118448 D179 P6 (102973) Boothline Road St Ded WSDP 7PSSDB 20.7 3.85 (3.95) 79.69 (81.77)
31118899 D179 P6 (88826) Clay/2nd St Sidewalk & Drainage Imprv 10PSSDA 20.66 3.85 (3.95) 79.54 (81.61)
31118734 D179 P6 (111305) CNP Fort Bend Substation 5PSLSB 20.68 3.85 (3.95) 79.62 (81.69)
31119118 D179 P6 (106140) Emberly Sec 7 5PSSDB 20.63 5.1 (5.2) 105.21 (107.28)
31118423 D179 P6 (106140) Emberly Sec 7 5PSSDB 20.67 5.1 (5.2) 105.42 (107.48)
31119390 D179 P6 (110580) Frost Bank Mission Bend 7PSSDB 20.65 4.8 (4.9) 99.12 (101.19)
31119210 D179 P6 (105324) FTBC MUD 250 WP #1 PHASE 2 & REMOTE 5PSSDB 20.64 5.6 (5.7) 115.58 (117.65)
31118525 D179 P6 (107296) Hallimore Ranch 2 WSD 5PSSDB 20.63 3.85 (3.95) 79.43 (81.49)
31119157 D179 P6 (107296) Hallimore Ranch 2 WSD 5PSSDB 20.68 3.85 (3.95) 79.62 (81.69)
31118760 D179 P6 (107296) Hallimore Ranch 2 WSD 5PSSDB 20.62 3.85 (3.95) 79.39 (81.45)
31118801 D179 P6 (107296) Hallimore Ranch 2 WSD 5PSSDB 20.62 3.85 (3.95) 79.39 (81.45)
31118495 D179 P6 (107296) Hallimore Ranch 2 WSD 5PSSDB 20.69 3.85 (3.95) 79.66 (81.73)
31118598 D179 P6 (107296) Hallimore Ranch 2 WSD 5PSSDB 20.59 3.85 (3.95) 79.27 (81.33)
31118473 D179 P6 (107296) Hallimore Ranch 2 WSD 5PSSDB 20.66 3.85 (3.95) 79.54 (81.61)
31119054 D179 P6 (81346) Indigo Sec 1 WSD & Paving 5PSSDB 20.74 4.2 (4.3) 87.11 (89.18)
31118552 D179 P6 (72822) Kelsey Seybold Fort Bend 5PSSDB 20.6 4.6 (4.7) 94.76 (96.82)
31118581 D179 P6 (105749) LCISD CTE Project - ROSENBURG 5PSSDB 20.62 4.2 (4.3) 86.6 (88.67)
31119072 D179 P6 (105749) LCISD CTE Project - ROSENBURG 5PSSDB 20.65 4.2 (4.3) 86.73 (88.8)
31118953 D179 P6 (105749) LCISD CTE Project - ROSENBURG 5PSSDB 20.65 4.2 (4.3) 86.73 (88.8)
31118777 D179 P6 (105749) LCISD CTE Project - ROSENBURG 5PSSDB 20.67 4.2 (4.3) 86.81 (88.88)
31118395 D179 P6 (105749) LCISD CTE Project - ROSENBURG 5PSSDB 20.7 4.2 (4.3) 86.94 (89.01)
31118980 D179 P6 (105686) Montclair Blvd Ph II 5PSSDB 20.74 4.8 (4.9) 99.55 (101.63)
31119094 D179 P6 (105696) Still Creek Ranch Sec 5 5PSSDB 20.61 3.15 (3.25) 64.92 (66.98)
31119187 D179 P6 (105696) Still Creek Ranch Sec 5 5PSSDB 20.59 3.15 (3.25) 64.86 (66.92)
31119043 D179 P6 (105696) Still Creek Ranch Sec 5 5PSSDB 20.51 3.15 (3.25) 64.61 (66.66)
31119030 D179 P6 (105696) Still Creek Ranch Sec 5 5PSSDB 20.65 3.15 (3.25) 65.05 (67.11)
31119015 D179 P6 (105696) Still Creek Ranch Sec 5 5PSSDB 20.66 3.15 (3.25) 65.08 (67.15)
31118717 D179 P6 (105696) Still Creek Ranch Sec 5 5PSSDB 20.43 3.15 (3.25) 64.35 (66.4)
31119435 D179 P6 (105696) Still Creek Ranch Sec 5 7PSSDB 20.57 3.15 (3.25) 64.8 (66.85)
31119356 D179 P6 (112483) Stonecreek Estates sec 13 10PSSDA 20.68 3.35 (3.45) 69.28 (71.35)
31118638 D179 P6 (109269) Texana Behavioral Health Clinic 10PSSDA 20.56 3.35 (3.45) 68.88 (70.93)
31118539 D179 P6 (104334) The 1824 Austin Point Sec 2 5PSSDB 20.6 3.85 (3.95) 79.31 (81.37)
31118607 D179 P6 (107445) Trillium 7 10PSSDA 20.66 5.1 (5.2) 105.37 (107.43)
31118509 D179 P6 (107445) Trillium 7 10PSSDA 20.63 5.1 (5.2) 105.21 (107.28)
31118655 D179 P6 (111791) Wharton Co Drainage Improvements - CMP LSB 20.73 8.4 (8.5) 174.13 (176.21)
Tickets count
Remaining tickets


Pendientes

Number Vehicle WorkFrom Order Product Ton Price Total