Details

Invoice


CreationDate
08/02/2024
Vehicle
D123 - Driver D123
Work
07-26-2024 to 08-01-2024
Check
Direct Pay
Bonus
Toll
Bonus + Toll
PDF (TestA TestRW) - EXCEL (TestA TestRW) -
  
Number Vehicle WorkFrom Order Product Ton Price Total
31108223 D123 P6 101578 5PSSDB 21.01 5.1 (5.2) 107.15 (109.25)
31108493 D123 P6 (106286) 717 const - B22-100 Term Contract for Concrete Pav 7PSSDB 21.11 5.85 (5.95) 123.49 (125.6)
31108435 D123 P6 (106286) 717 const - B22-100 Term Contract for Concrete Pav 7PSSDB 21.05 5.35 (5.45) 112.62 (114.72)
31108685 D123 P6 (98154) Austin Point Foundation Way 5PSSDB 21 3.85 (3.95) 80.85 (82.95)
31108270 D123 P6 (98154) Austin Point Foundation Way 5PSSDB 21.02 3.85 (3.95) 80.93 (83.03)
31108371 D123 P6 (98154) Austin Point Foundation Way 5PSSDB 21.03 3.85 (3.95) 80.97 (83.07)
31108349 D123 P6 (98154) Austin Point Foundation Way 10PSSDA 21.08 3.85 (3.95) 81.16 (83.27)
31108206 D123 P6 (98154) Austin Point Foundation Way 5PSSDB 21.04 3.85 (3.95) 81 (83.11)
31108124 D123 P6 (98154) Austin Point Foundation Way 5PSSDB 21.05 3.85 (3.95) 81.04 (83.15)
31108163 D123 P6 (98154) Austin Point Foundation Way 5PSSDB 20.96 3.85 (3.95) 80.7 (82.79)
31108099 D123 P6 (98154) Austin Point Foundation Way 5PSSDB 21.03 3.85 (3.95) 80.97 (83.07)
31108393 D123 P6 (91950) Brookewater 12 MORTARSD 21.1 4.6 (4.7) 97.06 (99.17)
31108518 D123 P6 (107335) CNP Waterhole Substation 5PSLSB 20.84 9.15 (9.25) 190.69 (192.77)
31108473 D123 P6 (105600) Cross Creek West Sec 8 7PSSDB 21.08 5.85 (5.95) 123.32 (125.43)
31108561 D123 P6 (103346) ESPERANZA SEC ONE 5PSSDB 20.99 3.35 (3.45) 70.32 (72.42)
31108411 D123 P6 (103346) ESPERANZA SEC ONE 5PSSDB 21.07 3.35 (3.45) 70.58 (72.69)
31108612 D123 P6 (103346) ESPERANZA SEC ONE 5PSSDB 20.99 3.35 (3.45) 70.32 (72.42)
31108454 D123 P6 (107475) HARVEST POINTE SEC 1 5PSSDB 20.98 4.2 (4.3) 88.12 (90.21)
31108580 D123 P6 (107475) HARVEST POINTE SEC 1 5PSSDB 21.11 4.2 (4.3) 88.66 (90.77)
31108082 D123 P6 (109828) KINGDOM HEIGHTS 5PSSDB 21.02 4.05 (4.15) 85.13 (87.23)
31108631 D123 P6 (96838) Lamar Transportation Center #3 5PSSDB 20.95 3.85 (3.95) 80.66 (82.75)
31108424 D123 P6 (96838) Lamar Transportation Center #3 5PSSDB 21 3.85 (3.95) 80.85 (82.95)
31108246 D123 P6 (96838) Lamar Transportation Center #3 5PSSDB 21 3.85 (3.95) 80.85 (82.95)
31108095 D123 P6 (96838) Lamar Transportation Center #3 5PSSDB 21.01 3.85 (3.95) 80.89 (82.99)
31108142 D123 P6 (95303) McCray Rd Reconstruction & Widening 7PSSDB 20.99 4.6 (4.7) 96.55 (98.65)
31108112 D123 P6 (91036) Rosenberg WWTP2 Sanitary Sewer Rehab 5PSSDB 21.04 3.85 (3.95) 81 (83.11)
31108599 D123 P6 (PM8462) SH36 NORTH @ Spur 10 - BIG CREEK 5PSSDB 21.02 3.23 (3.33) 67.89 (70)
31108672 D123 P6 (PM8462) SH36 NORTH @ Spur 10 - BIG CREEK 5PSSDB 20.93 3.23 (3.33) 67.6 (69.7)
31108317 D123 P6 (102832) SH36 NORTH @ Spur 10- 5PSSDB 21.1 3.23 (3.33) 68.15 (70.26)
31108333 D123 P6 (102832) SH36 NORTH @ Spur 10- 5PSSDB 21.07 3.23 (3.33) 68.06 (70.16)
31108290 D123 P6 (95317) Wharton US 59 Water and Wastewater Utility Relocat 5PSSDB 21.01 8.15 (8.25) 171.23 (173.33)
31108184 D123 P6 (95317) Wharton US 59 Water and Wastewater Utility Relocat 5PSSDB 21 8.15 (8.25) 171.15 (173.25)
Tickets count
Remaining tickets


Pendientes

Number Vehicle WorkFrom Order Product Ton Price Total